Dublin Ireland - UPS Upgrade
Scheduled Maintenance Report for MacStadium
Completed
The scheduled maintenance has been completed.
Posted 5 months ago. Jun 20, 2018 - 16:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 5 months ago. Jun 20, 2018 - 04:00 UTC
Scheduled
On Wednesday June 20th our Dublin Ireland data center partner will be upgrading their UPS system. Due to the redundancies in place we do not expect any interruption to MacStadium's services. We will have our Customer Support Technicians and Engineers in place in case of any issues.
Posted 5 months ago. Jun 19, 2018 - 11:13 UTC
This scheduled maintenance affected: Dublin Core 1 and Dublin Core 2.